Construction News

East Gym Addition

Interior fit-out work continues at the East Gym Addition. The 75,000 square foot addition includes three new gym courts, an expanded FitSpace, an elevated running track, and associated auxiliary spaces. Overall construction is expected to be complete in fall 2026. 

East Gym Addition

East Gym Track

A full reconstruction of the track and associated areas is underway. Work is expected to wrap up in August 2026.

Track renovation

Grace Hall- new residential hall

Grace Hall is located between the CIW and Mountainview communities. Work on the foundation is nearly complete and utility work continues. Grace Hall will house 362 students and is scheduled for completion in summer 2027. More information is available in this article.

Grace Hall

University Hall

Steel work is underway at the University Hall construction site. Utility relocation work continues as well. This project will add nearly 50 rooms to Binghamton’s catalog, with a total of just over 1,900 new seats. More information about the project is available in this article. Construction of the Lecture Hall is slated for January 2028 completion.

University Hall

University Hall

Chenango Room Addition

Steel work is complete and the contractor is focused on concrete floor installation and enclosing the building. The project includes a second-story addition housing a re-imagined Chenango Room and a dedicated event space including a terrace and outdoor seating. Panera is scheduled to open in June 2026 with other spaces opening as they are completed through September 2026.

Chenango Room Addition

Oneida Hall renovation

This is a critical maintenance project that includes asbestos abatement, rehabilitation and new layout for bathrooms, replacement of mechanical systems, new flooring, ceilings and lighting. Asbestos abatement and demo work is underway. Work will be complete for the fall 2026 semester. 

Science 3 renovation

Phase 2 and phase 3 of the Science 3 renovation is underway.  Work entails gutting existing spaces and providing new laboratories, classrooms and offices. Electrical, plumbing, fire and mechanical systems will be upgraded. Interior fit-out and mechanical rough-ins are progressing. Work will be complete in late 2027.